Hello Planners,
I am working with a schedule with three calendar IDs (6-days, 7-days and 5-days). In the summarization setting, P3 asks for calendar ID to use, what shall I use? Shall I use the the calendar ID which is assigned the most? (in this case, 6-day). Shall I be getting an accurate summary for the Percent Complete if P3 uses only one calendar id?
Please help. Regards.
Jun
I am working with a schedule with three calendar IDs (6-days, 7-days and 5-days). In the summarization setting, P3 asks for calendar ID to use, what shall I use? Shall I use the the calendar ID which is assigned the most? (in this case, 6-day). Shall I be getting an accurate summary for the Percent Complete if P3 uses only one calendar id?