Hello Planners,
I want to plot Man power Histogram in P6.
For example :
Activity = "Excavation" Duration = "1 month"
To perform this activity, I will need 5 persons per day (the same 5 persons will work continuosly during the month). but when plotting the Histogram, primavera multiply 5 by 30 days. I want to have for the month, a fixed number which is 5 persons.
I appreciate your support
I want to plot Man power Histogram in P6.
For example :
Activity = "Excavation" Duration = "1 month"
To perform this activity, I will need 5 persons per day (the same 5 persons will work continuosly during the month). but when plotting the Histogram, primavera multiply 5 by 30 days. I want to have for the month, a fixed number which is 5 persons.
I appreciate your support