i am rather new to ms project. have a few questions here. when i hv created the wbs, i give them a period each. then i assign the resources to them. when, for a specific task, i assign more resources, the time changed, it reduced. Nothing wrong with that as more resources means less time. however, each activities r of different productivity. and the time that i hv entered is based on the no. of people for that job and the amount of time required by that amount of people.
Say welding a section of plate, i put 2 welders and total required time is say 2 hours. what should i do then? i cant seem to find a place to input productivity for each activity in MSP. please advise, thanks.
Say welding a section of plate, i put 2 welders and total required time is say 2 hours. what should i do then? i cant seem to find a place to input productivity for each activity in MSP. please advise, thanks.