I have been working as a free lancer scheduler for 4 years cooperating with the contractor’s PM to develop a schedule for his project
lately, one of my clients asked me to prepare a report to explain the effect of some out-of-the-hand circumstances that caused delay to his project. Things like security problems (unfortunately common in my country),the consultant delay in approving the contractor’s submittals, problems in execution, request to change methodology of work etc...
the work is going fine but i am totally unaware how much to CHARGE my client...
of course it is hard for anyone to give me a figure knowing that each country has its own rates, but is there any sort of norm in these services? like a percentage, hourly rate, etc...
Your help is highly appreciated
Regards,
I have been working as a free lancer scheduler for 4 years cooperating with the contractor’s PM to develop a schedule for his project
lately, one of my clients asked me to prepare a report to explain the effect of some out-of-the-hand circumstances that caused delay to his project. Things like security problems (unfortunately common in my country),the consultant delay in approving the contractor’s submittals, problems in execution, request to change methodology of work etc...
the work is going fine but i am totally unaware how much to CHARGE my client...
of course it is hard for anyone to give me a figure knowing that each country has its own rates, but is there any sort of norm in these services? like a percentage, hourly rate, etc...
Your help is highly appreciated
Regards,