Hello
This is to highlight a common problem when planning curing time into a programme.
Concrete sets 24 hrs a day 7 days a week - curing time therefore needs a separate activity with the correct calendar attached.
This will however distort the critical path because if the curing period ends in the middle of a holiday then float will be generated before the next activity starts after the holiday.
Does anyone have an idea as to how this problem can be overcome.
Using a lead / lag link does not work because the link takes on the calendar of the preceiding activity.
Best regards
Mike Testro
This is to highlight a common problem when planning curing time into a programme.
Concrete sets 24 hrs a day 7 days a week - curing time therefore needs a separate activity with the correct calendar attached.
This will however distort the critical path because if the curing period ends in the middle of a holiday then float will be generated before the next activity starts after the holiday.
Does anyone have an idea as to how this problem can be overcome.
Using a lead / lag link does not work because the link takes on the calendar of the preceiding activity.
Best regards
Mike Testro