Hi guys,
Im new to P6 and planning, I am working on a Tunnel job in the UK and would like to show meterage on P6, for example -
Week 1,2,3 and 4 - 42 meters of tunneling is predicted each week, but week 5 only 36m because of bad ground expected. Is there a way I can manage progress like this and show it on P6?
The only way I can seem to manage this is by using excel spreadsheets, but id rather keep it on one software program.
Thanks