Hi,
I will explain my problem in points as:
1- Basically a schedule was made on P3 (by another planner)
2- The project duration is completed on Sep. 2008 , but work NOt.
3- The Schedule %Complete = 100 The Performance % Complete = 70
4- I am asked to make a revised schedule with extension of 12 Months.
5- I Convert the schedule to P6
6- I expanded the activities (added more items which was not there).
7- Added labor to activities
8- After completing the required extension time and Scheduling DD= 1-11-2008, I found that Schedule % complete and Performance % Complete is NOT Rolling as I expected.
9- Many WBS(for Example)which had 3 activities is 100%, is showing 0% at both Schedule & Performance % Complete.
So what is going On?????
May Any Help, and give solution ?????
I will explain my problem in points as:
1- Basically a schedule was made on P3 (by another planner)
2- The project duration is completed on Sep. 2008 , but work NOt.
3- The Schedule %Complete = 100 The Performance % Complete = 70
4- I am asked to make a revised schedule with extension of 12 Months.
5- I Convert the schedule to P6
6- I expanded the activities (added more items which was not there).
7- Added labor to activities
8- After completing the required extension time and Scheduling DD= 1-11-2008, I found that Schedule % complete and Performance % Complete is NOT Rolling as I expected.
9- Many WBS(for Example)which had 3 activities is 100%, is showing 0% at both Schedule & Performance % Complete.
So what is going On?????
May Any Help, and give solution ?????