Hi,
I have implemented P6.1 with the use of reflections for the Project Managers to update their reflections, before the Project Controls group checks these updates for quality and resource overallocations before merging these into the Source program.
This has its limitations;
- cant use duplicate resource/role allocations
- doenst merge some WBS name/code changes
- doesnt like deleted or re-numbered activity IDs
- merges project code changes without giving you the choice to do so...
Can anyone suggest a better way to do this?.. We would still like to maintain control of checking quality of schedule data before submitting to the "master program" which reports to management.
I suppose keeping a "what-if" copy for the PMs to work on, then just check and replace at the data date cycle - is the simple solution - but has its own administrative implications..
Thanks!
Rebecca
I have implemented P6.1 with the use of reflections for the Project Managers to update their reflections, before the Project Controls group checks these updates for quality and resource overallocations before merging these into the Source program.
This has its limitations;
- cant use duplicate resource/role allocations
- doenst merge some WBS name/code changes
- doesnt like deleted or re-numbered activity IDs
- merges project code changes without giving you the choice to do so...
Can anyone suggest a better way to do this?.. We would still like to maintain control of checking quality of schedule data before submitting to the "master program" which reports to management.
I suppose keeping a "what-if" copy for the PMs to work on, then just check and replace at the data date cycle - is the simple solution - but has its own administrative implications..
Thanks!
Rebecca