When using multiple calendars for different activities within a schedule (24hr calendars, standard 5 day 9-5 calendars etc) I get an extrenely high value in the total float column for activities with a 24hr calendar. The total float figure is longer than the remaining duration of the project. All activities are linked and I have put a must finish by constraint on the final activity - any ideas???