We are upgrading from P3.1 to P6. We have schedules with sub-projects that are updated remotely by the contractors and data is exchanged via PRD files. Once schedules are migrated to P6, will we still have this functionality? (Sorry if this has already been addressed, but the "search" function within forum threads isnt working and Ive spent as much time as I can on searching through all the previous posts...)