Hi guys,
I have received a Level 2 program for central Park for one of the project. It has actual dates in it and the guy who has prepared that, is not working anymore with us anymore.
When i updated the program and assigned the baseline, then baseline is not showing those actual dates. Instead it is using the logic and relationship assigned to derive the dates.
Is there any option, wherein we have the actual dates in baseline start and finish column.
Cheers,
Rav