a warm greetings to all:
this regarding the issue on developing a programme.as what i have noticed i can link the activities in both bar chart and PERT.
can you please help ma which of this two methods is better?
and lastly,how can i project the concrete pouring schedule in the project lay out,this activity is not continuos everyday.is it possible to be put repeatedly in every part of the building structures?
sample:
Concrete pouring in raft foundation after 1 week
concrete pouring in core walls from B$ to grnd floor.
What i mean which is the best way for me to put the concrete pouring activity while this is not continuous everyday.
your help is highly appreciated.
regards,
bon
this regarding the issue on developing a programme.as what i have noticed i can link the activities in both bar chart and PERT.
can you please help ma which of this two methods is better?
and lastly,how can i project the concrete pouring schedule in the project lay out,this activity is not continuos everyday.is it possible to be put repeatedly in every part of the building structures?
sample:
Concrete pouring in raft foundation after 1 week
concrete pouring in core walls from B$ to grnd floor.
What i mean which is the best way for me to put the concrete pouring activity while this is not continuous everyday.
your help is highly appreciated.
regards,
bon