Dear colleagues
I have encountered in P6 which has a wrong date calculation. The start date of the Successor is the same as that of the finish date of predecessor with a relationship of Finish to Start (FS). Have you encountered this before? what shall I do?
ie. Activity A has a duration of 3 days Start - 01SEP08 Finish of 03SEP08
Activity B (Successor of Activity which has a relationship of Finish to Start) has a duration of 4 days with Start date of 03SEP08 and completion date of 06SEP08.
The Start date of Activity B should be 04SEP08 not 03SEP08 by the relationship of F-S.
Hoping for your comments and solution for this matter.
regards
I have encountered in P6 which has a wrong date calculation. The start date of the Successor is the same as that of the finish date of predecessor with a relationship of Finish to Start (FS). Have you encountered this before? what shall I do?
ie. Activity A has a duration of 3 days Start - 01SEP08 Finish of 03SEP08
Activity B (Successor of Activity which has a relationship of Finish to Start) has a duration of 4 days with Start date of 03SEP08 and completion date of 06SEP08.
The Start date of Activity B should be 04SEP08 not 03SEP08 by the relationship of F-S.
Hoping for your comments and solution for this matter.
regards