Dear All
I have problem with P6 software.
The original duration of summary bar has not calculated based on activities original duration under mentioned summary bar.
I could correct this problem in p3 and when we set calendar ID in summary bar same as activities calendar ID , original duration will be corrected automaticly.
Also I set Actual start for those activities and original duration will be changed to "1" some times.
Could you help me and give your solution.