I am newly assinged to a project with a total delay 193 days
there are a lot of concurrency events in the project mean a lot of varation orders and at the same time the contractor has his own delay
its not clear in the contract who owns the float and which method to use in analysing the delay
there is an argument between the contractor and the consultant where the contractor trying to use Time impact analysis and the consultant is trying to use impacted as planned
Note( the baseline program is not approved and the project end date is already expired)