As a Planning Engineer from a Consultant, I received a Primavera progress report containing a 35 days delay and a letter of intent to claim for 120 days (Impacted As-Planned, reflecting events) with similar cut-off date from the Contractor. From my side, I will use the lesser duration of delays and further evaluate reductions.
Any comments/reactions?