Hi everybody
I need some help please. Im a new user in P6 and I need to move/copy a WBS structure from one project to another and I also need to delete the existing WBS structure in the target project.
Ive copied my new WBS over no problem, but I cannot delete the original structure as Im getting duplicate activities because of the 2 structures.
Any ideas?
Thanks
I need some help please. Im a new user in P6 and I need to move/copy a WBS structure from one project to another and I also need to delete the existing WBS structure in the target project.
Ive copied my new WBS over no problem, but I cannot delete the original structure as Im getting duplicate activities because of the 2 structures.
Any ideas?
Thanks