Hi
I created a resource pool last week to be utilised by 4 projects but when copying the resource pool to the first project, it will not copy all the fields or columns that I have created in the pool. e.g it copies the names, groups, Std Rate but not the region, departments etc. basically it only copies the generic MSP fields/columns and not the ones that I have added included in the pool.
Does anyone know why?
EV
I created a resource pool last week to be utilised by 4 projects but when copying the resource pool to the first project, it will not copy all the fields or columns that I have created in the pool. e.g it copies the names, groups, Std Rate but not the region, departments etc. basically it only copies the generic MSP fields/columns and not the ones that I have added included in the pool.
Does anyone know why?
EV