In my project We have agreed to orginal target programme which we treated as base line programme. and prepared the prolongation cost from orginal scheduled finish date. but there are three revision has done to target programme granting time extensions as client has done lot of design changes civil works got delayed as a result of that our MEP works got deleyed due to delay of possesion. more over partly possesion of site was given not according to the programme. Hence we could not give them a revised programme as the working areas and possesion date was not pre defined.
after 7 months from the Orginal finishing date Main contractor issued a target to finish programme and the remaining time is 3 months. Now we are doing with accelaration cost to finish the project in three months.
I have following questions.
1) As there is 3 revisions can they deduct our prolongation period as we are climing for the Original base line programme. (Project has a lot of deviations from this original programme.)
2). Since we have not submitted the revised programme will it effect to our prolongation cost claim I mean imposing penalties for not submitting revised programmes.
3) Since it is difficult to do time analysis can we prepare our claim base on the amount which we have submitted as possible EOT claims this has been submitted each month. My derived Cost is 70% from the informed possible EOT claims.
4)During the prolongation period Our wages has incresed by 15% of all staff. Can we consider the increased wage amount for the claim. as our Claim is prepared based on work input days and daily cost for the relevant staff.
5) Since our labours has not been idle as we have recived some part of the site to engage those people for work . I am ot going to claim the Labour cost for the prolongation period. Only the Prelimanary cost is considered Please correct me if I am wrong
GA
after 7 months from the Orginal finishing date Main contractor issued a target to finish programme and the remaining time is 3 months. Now we are doing with accelaration cost to finish the project in three months.
I have following questions.
1) As there is 3 revisions can they deduct our prolongation period as we are climing for the Original base line programme. (Project has a lot of deviations from this original programme.)
2). Since we have not submitted the revised programme will it effect to our prolongation cost claim I mean imposing penalties for not submitting revised programmes.
3) Since it is difficult to do time analysis can we prepare our claim base on the amount which we have submitted as possible EOT claims this has been submitted each month. My derived Cost is 70% from the informed possible EOT claims.
4)During the prolongation period Our wages has incresed by 15% of all staff. Can we consider the increased wage amount for the claim. as our Claim is prepared based on work input days and daily cost for the relevant staff.
5) Since our labours has not been idle as we have recived some part of the site to engage those people for work . I am ot going to claim the Labour cost for the prolongation period. Only the Prelimanary cost is considered Please correct me if I am wrong
GA