Dears
We got our NTP sometime back that had a total duration of the contract as 5 Months plus 15 days for Mobilization. Later on the SOW was revised and in the kickoff meeting it was prinicipally agreed by us that the contsruction time would be 4 months, plus 15 days for mobilization.
Now when we received our LOA, it says
Quote
........ Construction time is Four Months instead of Five Months and 15 days..............
Unquote
Now we are in dispute. We interpret this as 4 months instead of 5 months (Consruction Time), and 15 days for mobilization.
Please note that the above quote is exactly as it was typed in LOA.
Any thoughts?????
We got our NTP sometime back that had a total duration of the contract as 5 Months plus 15 days for Mobilization. Later on the SOW was revised and in the kickoff meeting it was prinicipally agreed by us that the contsruction time would be 4 months, plus 15 days for mobilization.
Now when we received our LOA, it says
Quote
........ Construction time is Four Months instead of Five Months and 15 days..............
Unquote
Now we are in dispute. We interpret this as 4 months instead of 5 months (Consruction Time), and 15 days for mobilization.
Please note that the above quote is exactly as it was typed in LOA.
Any thoughts?????