If an activity takes one day to complete and it starts on 20 May, when does it finish? Everybody knows it finishes on the same day.
But why on earth Microsoft Project show start date of 20 May and Finish date of 21 May for that activity? The bar is fully within 20 May, though.
Does anybody has solution how to get the same start and finish date for one date activity?
But why on earth Microsoft Project show start date of 20 May and Finish date of 21 May for that activity? The bar is fully within 20 May, though.
Does anybody has solution how to get the same start and finish date for one date activity?