I got a problem with P6. My company only uses cost loaded schedules with no true resource management involved. P6 calculates Actual Cost based either on the ratio of OD vs. RD or via manual input. I am trying to calculate Actual Cost based on Physical % Complete and not based on RD. Global changes are not working. I am sure some of you have run into this already.