Hai all,
A clause 14 program is submitted and not approved by the consultant after 4 months. Meanwhile the trial trench work has been completed by the contractor and could find that the water pipeline is too close and hence to be diverted before piling work. And now the contractors piling work for bridges is getting delayed due to diversion. But the consultant is telling the clause 14 is not approved and can not approve any variation. Who is correct? Please advice
Regards,
G.Kumar
A clause 14 program is submitted and not approved by the consultant after 4 months. Meanwhile the trial trench work has been completed by the contractor and could find that the water pipeline is too close and hence to be diverted before piling work. And now the contractors piling work for bridges is getting delayed due to diversion. But the consultant is telling the clause 14 is not approved and can not approve any variation. Who is correct? Please advice