hi all:
When I use this function Update Progress in P6,I met a question. The remaining duration of activities always equal to the original duratin, not equal to (finished date-data date).
Any help is appreciate.
Thanks & regard
When I use this function Update Progress in P6,I met a question. The remaining duration of activities always equal to the original duratin, not equal to (finished date-data date).
Any help is appreciate.
Thanks & regard