Dear All,
Im not really sure about this but it happened when Im running a schedule with a certain activity that has an actual start earlier than the Data Date. The bar still goes with the Data Date and hasnt started on the Actual Date, though the status shows an actual duration and a remaining duration.
Note: there is no % progress, only actual start; scheduled by retained logic
any idea?
Im not really sure about this but it happened when Im running a schedule with a certain activity that has an actual start earlier than the Data Date. The bar still goes with the Data Date and hasnt started on the Actual Date, though the status shows an actual duration and a remaining duration.
Note: there is no % progress, only actual start; scheduled by retained logic
any idea?