Dear Planners,
I dont really know if im doing this right, but I want to know the possibilities if I set a baseline that has actuals and constraints (inavoidable due to Engineering and Procurement).
1. Can I set a Baseline Schedule in P6 that has actuals and constraints? (I believe I can, but what would be the effect?); i.e. in Timesheets and time schedule?
2. Can it be justifiable setting a Baseline that has actuals and constraints? How?
I dont really know if im doing this right, but I want to know the possibilities if I set a baseline that has actuals and constraints (inavoidable due to Engineering and Procurement).
1. Can I set a Baseline Schedule in P6 that has actuals and constraints? (I believe I can, but what would be the effect?); i.e. in Timesheets and time schedule?
2. Can it be justifiable setting a Baseline that has actuals and constraints? How?