Hello PPs,
Is there anyone who used both Primary and secondary Constraint in the case of Finish Milestones, that havent any predecessor ?
What do you put in Primary and in Secondary ? In which order do you put "Finish On or Before", and "Finish On or After" ?
Are there any other cases (for tasks ?)we could use them without complicating the critical path analysis ?
Best regards.
Patricia