In P3(Version 3), the sub projects were added to the group at the time of creating a project. In P6 I did not find anything like sub projects. One way is to create Node under EPS and open all the projects at one time. But as in P3 we cannot assign a Baseline to the materproject in P6. If any one has knowledge about it, please share with us all.
Regards,
Azhar
Regards,
Azhar