Is there a different calculation in the Planned Value Cost field within the activities view in P3e and the Planned Value Cost field in Projects view? In doing monthly reports, i have some variances between the two sets of figures even though the plan is the same and the baseline attached is the same.
I have checked project settings, Planned Start and Finish Dates, BL start & Finish Dates, BL costs etc. but cant see why the two values would be different.
Cheers
Richard Rowberry
I have checked project settings, Planned Start and Finish Dates, BL start & Finish Dates, BL costs etc. but cant see why the two values would be different.
Cheers
Richard Rowberry