In one of the Infrstructure projects, I m working on with scope covering Chilled water pipeline, storm water, sewerage, Gas pipeline, Telecommunications, HVL, LVL, irrigation and other services, after six months, there were huge changes in design and profile levels of all services and for which extension of time need to be submitted to Client.
I hav done most of d planned and mitigated events using Global change, but now I hav to insert two activities in each district / road section.
Act. No. 01 - Branch Excavation works (Apart from Header Lines, which was there in the original scope)
Act. No. 02 - Branch Pipe Laying Works
Now, Act. No. 01 shud come after an activity called Patial backfilling upto duct level and
Act. No. 02 before Hydrotesting of sections with FS relationship with previous activity.
there r almost 50 + sections wherein I need to insert these activities and change the logical relationships.
Is there any way out to have some program or macros designed to insert these activities at appropriate locations with new relationships.
GUYS Urgent plz. Its taking too much of time to insert and define relationship manually for all sections.
Cheers,
Ravi
I hav done most of d planned and mitigated events using Global change, but now I hav to insert two activities in each district / road section.
Act. No. 01 - Branch Excavation works (Apart from Header Lines, which was there in the original scope)
Act. No. 02 - Branch Pipe Laying Works
Now, Act. No. 01 shud come after an activity called Patial backfilling upto duct level and
Act. No. 02 before Hydrotesting of sections with FS relationship with previous activity.
there r almost 50 + sections wherein I need to insert these activities and change the logical relationships.
Is there any way out to have some program or macros designed to insert these activities at appropriate locations with new relationships.
GUYS Urgent plz. Its taking too much of time to insert and define relationship manually for all sections.
Cheers,
Ravi