I have assigned certain resources to activities and i plot budgeted units graphs with the data.But when the activity gets an actual finish before the early finish of the activity, the budgeted units still are shown on early dates only.My question is that when i plot the graph for forecast of budgeted quantity, primavera is including the quantities of activities that have already finished hence a wrong forecast of required quantities.What fields do i need to use to represent the correct data or do i need to change any settings???