I have taken over a project and one of the activities is 100% complete.
It has a resource budget cost of £1000 and an expense budget cost of £500.
The earned value cost is £0.00
Why is there no earned value?
It has a resource budget cost of £1000 and an expense budget cost of £500.
The earned value cost is £0.00
Why is there no earned value?