According to clause 14.2, the Engineer can ask the Contractor to submit a revised programme if the actual progress doesnt conform to the original programme. I have two enquieries:
1) Is the new revised programme considered a "new baseline"? or we have to stick to the original consented baseline.
2) If the original baseline cannot be contractually chenged, how it can be used as a reference to assess claims even it is not doable anymore?
Thank you
1) Is the new revised programme considered a "new baseline"? or we have to stick to the original consented baseline.
2) If the original baseline cannot be contractually chenged, how it can be used as a reference to assess claims even it is not doable anymore?
Thank you