Hello all. Im a virgin to the site so bear with me if I contravene any protocols.
The problem I have is that my client does not want to invest in MSP Server but I have to manage a number of separate plans. These have logic links between them. When I make a change to a plan name (ie revision update) I then lose the links (not unsurprisingly). Is there a way to get MSP to easily recognise the changes or, preferably automatically make them ?
Thanks
Bob
The problem I have is that my client does not want to invest in MSP Server but I have to manage a number of separate plans. These have logic links between them. When I make a change to a plan name (ie revision update) I then lose the links (not unsurprisingly). Is there a way to get MSP to easily recognise the changes or, preferably automatically make them ?
Thanks
Bob