Hi planners,
I have a level one schedule, that I have used resource curves on, seeing I dont have the detail to get a resource histogram that is not linear.
When I made a copy of the schedule, the resource curves have disappeared, so I added the one I was using, but now nothing happens to the resource curve, it remains linear.
Any one with suggestions / ideas?
I know using a resource curve is a quick fix, but I dont have the detail to develope a full schedule.
Thanks, Kevin, Perth Australia