Dear fellow planners,
Im curious as to how to select the best resource profile
for a contingency level of effort within P3e.
There is a default profile called Contingency.
However, some Project managers wish to forecast all their contingenct at the very end i.e. (last 20% of the level of effort duration).
The obvious reason is that the PMs wish to use this conting. budget once all other project budgets have dried up i.e. at the later stages of the project.
Any guidance on the best profile to select and why??
Cheers
Neil.