I think this subject might been discussed earlier but i couldnt get the exact answer to clear my doubt.
Eg: Senario: Project Early start date is : 01.01.2007
Early finish date : 10.01.2007
Total Duration 10 Days
Data date is 05.01.2007
Now, in this senario, the duration % complete would be 50% on 5th Jan. But in reality the physical % completed (the real work done in the plant) would be 30 %. Now , i want to make comparison chart to show what duration is sofar completed and what physical progress we have acheived. In p3e i seen each day when you update the schedule with aplly actuals the project will show the duration % complete automatically. Now if you put the column of physical % complete that will be the same of the duraiton % complete. I really get confuse on those stuff. What i want to know is . The reality work completed would be entered in to a column manually and how can i see the total % of that. I can enter the real work % in to a user created column for each activity but i have to get the total % of that all i entered. Please let me clear my doubt. I would prefer to have discussion from simple theory.
Thank you
Suresh
Eg: Senario: Project Early start date is : 01.01.2007
Early finish date : 10.01.2007
Total Duration 10 Days
Data date is 05.01.2007
Now, in this senario, the duration % complete would be 50% on 5th Jan. But in reality the physical % completed (the real work done in the plant) would be 30 %. Now , i want to make comparison chart to show what duration is sofar completed and what physical progress we have acheived. In p3e i seen each day when you update the schedule with aplly actuals the project will show the duration % complete automatically. Now if you put the column of physical % complete that will be the same of the duraiton % complete. I really get confuse on those stuff. What i want to know is . The reality work completed would be entered in to a column manually and how can i see the total % of that. I can enter the real work % in to a user created column for each activity but i have to get the total % of that all i entered. Please let me clear my doubt. I would prefer to have discussion from simple theory.
Thank you
Suresh