Guys,
I have this problem once again! the other partys consultants are looking for a Critical Path on the As Built programme. I am trying to tell them that this is not necessarily the Critical Path AS AT THE TIME OF THE DELAY and that the Critical Path shifted many times during the project but to no avail.
what is the best argument I can put forward to prove how wrong they are? are there any past cases to simply prove that this is incorrect?
I have this problem once again! the other partys consultants are looking for a Critical Path on the As Built programme. I am trying to tell them that this is not necessarily the Critical Path AS AT THE TIME OF THE DELAY and that the Critical Path shifted many times during the project but to no avail.