Hi
Ive searched through hundreds of threads but cant seem to find an answer to my problem.
The client Im working for would like to show resources as individuals against each activity - including either the no of men or the budgeted hours. Alongside the gantt chart view.
Eg.
Activity 1-Start-finish-Eng(20hrs)Plan(10hrs)Fitter(24hrs)
OR
Activity 1-Start-finish-Eng(2)Plan(1)Fitter(2) where the no. in brackets equals the no. of men.
Ive tried to replicate this in the resource assignment view but it creates multiple lines for the resources and I just want them on one line per activity. Ive also tried the export resources and reports but ideally they want the info alongside the gantt chart.
They can currently show this information using AMS Realtime but would like to move to P3e - if this resource display is possible.
Cheers
Ive searched through hundreds of threads but cant seem to find an answer to my problem.
The client Im working for would like to show resources as individuals against each activity - including either the no of men or the budgeted hours. Alongside the gantt chart view.
Eg.
Activity 1-Start-finish-Eng(20hrs)Plan(10hrs)Fitter(24hrs)
OR
Activity 1-Start-finish-Eng(2)Plan(1)Fitter(2) where the no. in brackets equals the no. of men.
Ive tried to replicate this in the resource assignment view but it creates multiple lines for the resources and I just want them on one line per activity. Ive also tried the export resources and reports but ideally they want the info alongside the gantt chart.
They can currently show this information using AMS Realtime but would like to move to P3e - if this resource display is possible.
Cheers