Hi Guys,
In my school days I learned the CPM is created as a result of forward and backward pass computation.
In this todays modern world with the aide of powerfull computers the CPM is totally violated in a sense it does not obey the proper rule of planning.
What i want to say , others are making or they first identify by themselselves where the CPM will run thru along the schedule not a CPM as a result of a computation.
My Question: Can CPM be indentify first or after computation