Can anyone please advise me on exporting data for S Curve Generation
After loading weightage or Resources and unit cost, I use CL 03 Cost loading reports.
I generally use usuage total in time scale and what I oberve during updating in later stage some of the distribution are higher side and end up showing behind schedule even though project on time.
Can anyone advise me is the use of CL - 03 Cost loading reports is correct? and out of 3 usuage - total, peak & average - which one to use.
I would appreciate for your feedback.
Many thanks & cheers