Hi, I am in a situation which needs help from our experts...
In our Infrastructure Project, The project is delayed due to changes in design and we have applied for an EOT. Meanwhile Employer wants a priority portion of the project to be accelerated to complete. We fail to agree on a lumpsum price and agreed to work on "Actual accelerative measure will be compensted " basis.
Now without awarding EOT, Employer wants a revised completion programme discounting the accelerated measures proposed to be taken...( Sounds very complicated right - for me too )How to go about it.
In our Infrastructure Project, The project is delayed due to changes in design and we have applied for an EOT. Meanwhile Employer wants a priority portion of the project to be accelerated to complete. We fail to agree on a lumpsum price and agreed to work on "Actual accelerative measure will be compensted " basis.
Now without awarding EOT, Employer wants a revised completion programme discounting the accelerated measures proposed to be taken...( Sounds very complicated right - for me too )How to go about it.