there are fill cell in P3 if i want to put the same duration in many activities so i hilight for duration cells and right click and press to fill cell
duration appear automatic in all activities
my question now how i use the same option in P3E
or where is fill cell in P3E
thank you
duration appear automatic in all activities
my question now how i use the same option in P3E
or where is fill cell in P3E
thank you