Hi,
I am doing a baseline comparison on someone elses plan.
How is it possible to have and Earned Value cost that is higher than the budgeted cost for a WBS summary level?
Isnt the EV calculated from the activity % complete multiplied by the baseline budgeted cost?
(With performance technique set to Activity % complete)
I have the baseline assigned as the project baseline in the assign baseline dialog box.(Which I believe is the baseline EV calcs work from)