Hi,
Have any of you come across the following error message when trying to change the type of resource?
"The resource type cannot be changed because this resource is currently assigned to one or more projects. The project plans and baselines would be invalidated"
If so does anyone know a way around it?
We currently have a number of projects imported from Suretrak where all our resources were set to Labour however in P3e it would probably be better for us to have cranes and tooling as non-labour.
Have any of you come across the following error message when trying to change the type of resource?
"The resource type cannot be changed because this resource is currently assigned to one or more projects. The project plans and baselines would be invalidated"
If so does anyone know a way around it?
We currently have a number of projects imported from Suretrak where all our resources were set to Labour however in P3e it would probably be better for us to have cranes and tooling as non-labour.