Hi,
I have entered resources in my resource table with both normal and max limits. Also assigned resources to each activity.
When I level, activities are not delayed due to lack of available resources. P3 does not seem to use the resource limits to delay start of activities.
On the Level dialog box, the Project Leveling entries are greyed out.
Can anyone help with this problem?
thanks,
Phil