Hi,
A JCT98 private with quantities contract.
Sub Contract ground work & drainage.
Sub Contract Sum say £270,000.00
Main Contractor was issued an AI to remeasure part of the bill.
Main Contractor did not issue this AI to Groundwork sub contractor.
At Sub Contract Final Account, is it to be re-measured or pay as Sub Contract Sum as per order?
If re measure & price up, the Sub Contract Final Account came to £230k(Measured Work + £40k Variations (CVI & SI)
What are argument points (for or against)& why?
Cheers