I am involved in a construction project wherein significant design changes were necessary to make the building structurally sound. The current delay is expected to be approximately 8 months. Contractor and I discussed re-baselining their schedule to advanced levels of detail to a) illustrate the full impact; and b) provide better detail with which to build an acceleration/recovery schedule. Client has indicated that they will reject any schedule which differs from the approved baseline schedule - even if the re-baseline includes the remaining work activities from the baseline.
Anyone familiar with legal precedent on contractors opportunity to rebase projects once such significant changes arise? Thanks.
Anyone familiar with legal precedent on contractors opportunity to rebase projects once such significant changes arise? Thanks.