Hi Guys
I’ve found some thing really strange (at least for me), I want to relate to activities with SF (Start to Finish) relationship. I call those activity A and B and duration of both is 2 days.
A / Predecessor: B SF
A>>> start date: 2-Dec-2007 8:01 AM & finish date: 4-Dec-2007 8:01 AM
B>>> start date: 4-Dec-2007 8:00 AM & finish date: 5-Dec-2007 16:00 PM
As I know, “A” should be finished before “B” will be started but It’s not happened!!
And “A” is continued up to 1 minute after “B” will be started.
My questions are:
1-Why “A” started on 8:01 am instead of 8:00 am?
2-How “A” can be started on 8:00 am without using any Constraint or Lag? (It will be caused that “A” will be finished on time ex: 3-Dec-2007 16:00 pm).
Thanks in advance
amir
I’ve found some thing really strange (at least for me), I want to relate to activities with SF (Start to Finish) relationship. I call those activity A and B and duration of both is 2 days.
A / Predecessor: B SF
A>>> start date: 2-Dec-2007 8:01 AM & finish date: 4-Dec-2007 8:01 AM
B>>> start date: 4-Dec-2007 8:00 AM & finish date: 5-Dec-2007 16:00 PM
As I know, “A” should be finished before “B” will be started but It’s not happened!!
And “A” is continued up to 1 minute after “B” will be started.
My questions are:
1-Why “A” started on 8:01 am instead of 8:00 am?
2-How “A” can be started on 8:00 am without using any Constraint or Lag? (It will be caused that “A” will be finished on time ex: 3-Dec-2007 16:00 pm).
Thanks in advance
amir