i need a clear cut answer on this issue:
i have linked all nominated subcontractor activities accordingly
1. Date of nomination
2. Preparation of shop drawing and material submittals
3. Approval for the above
4. Lead time for material arrival at site (Here i have put free float constraint and connected to the exact commencement of activities, which i feel is the correct logic.
But our Consultant is objecting that, since they feel that any constraints should not be in the program.
Kindly advice me how do other planners connect this type of relationship if u are not using free float constraint.
And also, I want to know that, can I justify my free float constraint contractually to consultant?????
Haresh
i have linked all nominated subcontractor activities accordingly
1. Date of nomination
2. Preparation of shop drawing and material submittals
3. Approval for the above
4. Lead time for material arrival at site (Here i have put free float constraint and connected to the exact commencement of activities, which i feel is the correct logic.
But our Consultant is objecting that, since they feel that any constraints should not be in the program.
Kindly advice me how do other planners connect this type of relationship if u are not using free float constraint.
And also, I want to know that, can I justify my free float constraint contractually to consultant?????
Haresh